CSAH36 Weekly Construction Update from Bolton & Menk:
Week of August 15
• The contractor installed storm sewer along Ferry Street from 2nd Street to 3rd Street.
• Installed sanitary sewer and watermain along Main Street from Cantwell Street to Maag Street.
• Installed a retaining wall on the east side of Main Street from Davis Street to Cantwell Street.
• Completed sanitary and water service work along Ferry Street between 2nd Street and 3rd Street.
• Installed lighting conduit along Main Street from Davis Street to Cantwell Street.
• Installed the lighting cabinet and started installing lighting wire along Main Street from Smith Street to Davis Street.
Week of August 22
• The contractor will finish installing the watermain along Main Street from 2nd Street through Maag Street. Following the installation of the watermain, the contractor will complete the sanitary sewer and water services along this block of Main Street. After the installation of the services, the contractor will work on storm sewer from 2nd Street through Maag Street.
• The contractor will work on grading the roadway along Ferry Street from Main Street to 4th Street in preparation for curb and gutter the week of August 29th.